Field Production & Operations · Daily Tasks
Post-Construction
Must be completed immediately after the project is done.
Production Closeout
Small equipment and tools back on trucks
Check site for trash and debris (housekeeping)
Wheel stop spikes
Trash
Construction Debris (curb line, grass, islands)
Notify onsite rep finished for day, inform of any constraints (don’t drive on concrete 72 hours)
Ensure barricades are in place
Replace fixtures (cart corrals, signs, trash cans, etc)
Verify correct scope fully completed
Verify quality of work (quality check)
Segregation
Proper joints
Any damage to surrounding areas
Loading Up & Heading Out
Monitor weather (lightning, raining, winds, etc) before traveling
Secure equipment to trailer
Verify trailer is secure to truck
Seatbelt use is mandatory
Hydration
Proper lifting technique
No horseplay
If Traveling:
Verify personnel are accounted for (curfew if traveling)
Buddy system – don’t go out alone
If Leaving Equipment On-Site
Secure the equipment in a safe location
Barricade or lock trailers as best as possible
Disable master switches and take out the keys
Daily Job Information
Include truck and material tickets and quantities
Include truck and equipment inspection sheets
Photos
Wide shots of overall project – be proud to show your hard work
Close shots of specific items (8 bollards installed = 8 photos)
Progress photos
Depth photos
Labor Hours
Clean Equipment
Clean Daily – Upload photo
Use right product for the task
Label product for equipment or truck use
Personal responsibility – operator/driver
Clean equipment runs better and lasts longer